Poland Concludes Hearings to Annul GreenX Arbitration Awards in Singapore and UK

Stories are grouped across languages, rewritten into a fixed editorial format, and linked to original sources.

TL;DR

  • Hearings completed on Poland's applications to annul GreenX's arbitration awards in Singapore and England.
  • Expected rulings on annulment in both jurisdictions by Q1 2027.
  • GreenX received cost reimbursement from Poland for Singapore proceedings.
  • GreenX is preparing enforcement actions if annulment attempts are denied.

Overview

Hearings have ended in court proceedings in Singapore and England concerning Poland's motions to set aside arbitral awards issued in favor of GreenX Metals Limited.

These awards stem from investment treaty claims under the Australia-Poland BIT and the Energy Charter Treaty related to the Jan Karski mining project.

GreenX is preparing for the enforcement of the awards, should Poland's set-aside challenges fail.

Related Stories: Renewables Arbitration Awards Threaten Spain's Assets Amid World Cup Preparations

What Happened

The hearings in proceedings brought by Poland to annul arbitral awards in favor of GreenX Metals Limited have concluded in both Singapore (before the appellate court) and England (in the court of first instance).

The awards in question were issued after an international arbitral tribunal found Poland liable under both the Australia-Poland bilateral investment treaty (BIT) and the Energy Charter Treaty (ECT) related to the Jan Karski project, ordering Poland to pay approximately GBP 252 million under the BIT award and GBP 183 million under the ECT award, with overlapping payment obligations.

Poland's set-aside applications challenge the validity of these awards on jurisdictional and procedural grounds, rather than the merits. The Singapore International Commercial Court already rejected Poland's challenge to the ECT award at first instance in January 2026 and granted GreenX costs, which Poland paid in full (approximately AUD 1.6 million).

Appeals and final decisions by the Singapore Appellate Court and the English Commercial Court are expected in Q1 2027. GreenX is advancing preparatory steps for enforcement, having retained LALIVE and asset tracing experts, anticipating further recovery actions in multiple jurisdictions should court challenges fail.

Context

The arbitral awards at issue arise from disputes over the Jan Karski mining project and involved claims under both the BIT between Australia and Poland and the Energy Charter Treaty.

The post-award phase now includes court challenges to the validity of those awards as well as preparations by GreenX for international enforcement, common steps in investor-state arbitration when significant damages are at stake.

Why It Matters

  • A decision on these set-aside proceedings will determine whether GreenX can enforce over GBP 250 million in arbitral awards against Poland.
  • Successful enforcement could have material financial implications for both the claimant and the Polish state.
  • The case illustrates the post-award set-aside and enforcement process in investor-state arbitration.